January 2020 Update

Happy New Year! We are excited for all the work on the YMCA recreation center that will begin in 2020 and wish everyone a happy and successful New Year!

We were able to negotiate a guaranteed maximum price with our contractor.   We finalized and signed Guaranteed Maximum Price Amendment with Adolfson & Peterson Construction.  This contract will help us stay in budget for the project and ensure a maximum price for our contract.

We confirmed with BRS the gas load for phase 1 and sent it to Xcel for verification.

Xcel is ready to begin the electrical work and we have authorized the work to begin.  We authorized the Frost Agreement and Electrical and Gas contingency documents.