September Update

Can you believe we are almost ready for our Topping Out ceremony? The Topping Out Ceremony commemorates the structural completion of the facility. Save the date for September 25th from 3-5pm. An invite will go out with all the details and we hope to see you and your family there!

September Construction Updates:

  • Lower level structure – interior masonry is almost complete with partition walls
  • All steel beams on south side are 100% installed 
  • Starting rebar on Sept 14th
  • Cold form framing is getting ready to start
  • Form and Pour Pool Equipment housekeeping pads will take place in September
  • Backfill Pool permitter complete
  • Installed plumbing for future drains 
  • Pour structural slab the week of September 7
  • Steel joyce is painted and coming to site
  • Crawl space and electricians are beginning to rough in the crawl space
  • Begin putting in support for air conditioning, fire and sprinkler
  • Tall exterior concrete walls 98% completed and will be complete by 10/1
  • Pouring pool structural slab 9/7
  • Water truck onsite full time to combat dust – water morning, lunch and evening to keep it down
  • Curb and gutter is done and asphalt is poured
  • Masonry walls and portion walls in the locker rooms are being completed