October Update

Below are some of the key tasks completed over the last month:

  • Main level deck was split into 2 separate pours and both are now completed
  • All main level steel and deck is now in place
  • Backfill going on around the building
  • Roof steel is nearing completion and all roof josts have been installed
  • Overhead ceiling work for MEP and FIre Sprinkler trades is now underway on the lower level
  • Rough in of the pool and touch ups taking place
  • HPC coatings for beam pockets in the Natatorium was completed this week prior to roof joist being set in place.
  • We are prepping for building envelope work to begin
  • Retaining wall is complete and now preparing to seed the site to establish stabilization before winter hits
  • Framer is starting on the upper level
  • Nearing completion of lower level plumbing rough ins
  • Electrical rough-ins within the crawl space areas are currently in progress

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: