The foundation walls are going up! As the walls go up you can see the footprint of the building starting to take shape. You can start to visualize the walkout layout and where the upper parking lot will be on the east side.
Here is some of the progress that occurred over the last month:
- Foundation tall walls are almost completed 1 more wall to complete then they will start grade beams
- Dry utilities, electric and temporary power is in
- Storm Sewer is 75% complete
- The sanitary sewer is 100% complete with utility contractor
- Water main is 90% complete
- Underground lighting is being trenched for upper east parking lot
- Conduits are run for fiber cable and Comcast
- Start trenching and sleeving for asphalt and parking lot