Look at all the progress from May until June! The project is staying on track and on schedule.
Tall concrete walls are 84% completed.
Foundations are 63% complete into the perimeter drain.
Working on the next round of grade beams and are at 21% completed.
Pool structure – 10% completed – underground plumbing in pool 80% done.
Gas phone and internet – ADP is boring from south east corner of the site
Rebar is being drilled
We had a few rainy days onsite and stormwater draining is working effectively and continues to pass inspection.
Community Involvement – Viewing platform is being created next week and will be up the week of June 22nd. Residents are welcome to stop by the site and watch the construction from the viewing platform.