November Update

November marks some big activities on site as the roof is being completed and interior work can begin. Below are the construction updates for November:

  • Framing is beginning in the lower level
  • Ceilings in the locker room areas are beginning
  • Main level rough ins and straps are getting started
  • Rough in Pool overhead electrical completed
  • Rough in HVAC ductwork
  • Rough in Pool fire sprinkler system
  • Metal panel screens
  • Roof level steel beams and trusses have been placed
  • Installing roof curbs
  • Flat roof installation and sloped roof installation
  • Layout interior stud walls